Metiskow

Solar Farm

This project was developed by Aura Power and is now owned by a local Indigenous Group.

The renewable energy facility includes 26 MW of solar capacity with a 100MW battery energy storage system located on privately-owned land.

The facility will use approximately 521,000 modules on single-axis tracker systems, 64 inverter and transformer stations, an electrical collection system, and access roads. A substation will connect the Project to the Alberta Interconnected Electric System (AIES).

Latest News

January 2023

Initial Stakeholder Notification

January - March 2023

Public Consultation

March 2023

AUC Application

July 2023

Development Permit Application

September 2023

Anticipated Development Permit Approval

Spring 2024

Start of Project Construction

Key Facts & Benefits

48000

Amount of homes powered with clean renewable energy

100000

Tonnes of CO2 offset annually

80000

Equivalent number of electric cars powered per year

Contributes to local and national targets

500 full time jobs created

Local economic boost

Local School Visits

Property taxes paid to the County

Our Proposal

The preliminary site layout takes into account various constraints such as: The preliminary site layout takes into account various constraints such as:

• Bird migration surveys

• Wetland setbacks

• Wildlife setbacks

• Road setbacks

• Property line setbacks

• Transmission line right-of-way and setback

• Oil & Gas setbacks

• Efficient use of land

We undertook a number of surveys to help inform our proposal. These included:

A detailed Noise Impact Assessment (NIA) has been completed to ensure the Project adheres to Alberta Utilities Commission (AUC) Rule 012: Noise Control. A copy of NIA will be included in the AUC application.

A glare assessment has been completed to assess potential for glare at residences and along local roads and we are committed to mitigating glare concerns.

Comprehensive environmental studies including wildlife studies, vegetation studies, wetlands delineation and habitat mapping have been completed for the Project.

•The results and potential mitigation were submitted to Alberta Environment and Protected Areas (AEPA).

•AEPA issued a Renewable Energy Referral Report in December 2022 giving the Project an overall risk ranking of Low

•Historical Resources Act approval has been applied for and approval is expected in Q1, 2023.

At the end of the project’s life, it will be decommissioned or re-powered. When decommissioned, equipment such as the solar modules and racking will be salvaged and recycled. Solar installations primarily use steel posts that are driven or screwed into the ground, and only use concrete foundations for inverters and the collector substation. Reclamation will be consistent with the Alberta Conservation and Reclamation Directive for Renewable Energy Operations or applicable legislation at the time. The landowner can resume normal agricultural operations following the 35 + year lifespan of the solar project. A decommissioning plan and an initial conservation and reclamation plan will be developed for the Alberta Utilities Commission and Cypress County

Projected Views

Contact Us

Your feedback is very important to us. Please leave a comment and one of our project team will get back to you as soon as possible.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.